Plant foundations, Surat

The brief

What made this one difficult

The plant could not shut down. Every foundation sat between live pipe racks, with permit-to-work restrictions and a two-shift window at weekends.

Contaminated ground meant spoil had to be segregated and disposed of under a documented regime.

What we did

The package, step by step

One contractor from the borelog to the final test certificate.

  1. Constrained investigation

    Compact rigs working inside pipe racks with hot-work permits for every hole.

  2. Deep pits

    Four sump and pump pits to 9 m, propped and cast in weekend windows.

  3. Foundations

    Machine bases and tank ring beams cast to tolerance beside running plant.

  4. Spoil management

    Segregated, tested and disposed of under a documented waste regime.

0 hrs

Production stopped

9 m

Deepest pit

18

Weekend windows used

100%

Spoil documented

On site

Photographs from the works

Plant foundations, Surat — photograph 1
Plant foundations, Surat — photograph 2
Plant foundations, Surat — photograph 3
Plant foundations, Surat — photograph 4
Plant foundations, Surat — photograph 5
Plant foundations, Surat — photograph 6

“They planned around our shutdown calendar instead of asking us to plan around theirs.”